It was another busy week at the construction site, as multiple trades efficiently shared the space available. Here are some of the highlights featured in the pictures below:
– small scale interior excavation
– installation of plumbing for several varieties of drains
– interior walls (complete with doorways) began popping up
– the first layer of roofing material was installed
– framing for our rooftop HVAC fencing appeared
– our new elevator began to take shape

20131002-215253.jpg

20131002-215359.jpg

20131002-215513.jpg

20131002-215705.jpg

20131002-215825.jpg

20131002-215917.jpg

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s